Example: Project Scheduling
What would be the decision variables of the mathematical model? The objective function? The constraints?
Answer:
- Decision variables: which activities to expedite and by how much, and when to start each activity
- Objective function: minimize project completion time
- Constraints: do not violate any activity precedence relationships and do not expedite in excess of the funds available.